MEZCLA CONCRETO 1:2:1 4000 PSI - 28,0 Mpa
M3
Materiales
| Código |
Descripción |
Unidad |
Cantidad |
Valor Unit |
Total |
Acción |
| 1062 |
GASOLINA CORRIENTE |
GLN |
0.1000 |
$16.758 |
$1.676 |
|
| 529 |
CEMENTO GRIS PORTLAND |
KG |
480.0000 |
$650 |
$312.000 |
|
| 114 |
AGUA |
LT |
210.0000 |
$78 |
$16.380 |
|
| 207 |
ARENA DE TRITURACIÓN Y/O ARENA GRUESA DE RIO |
M3 |
0.8700 |
$52.278 |
$45.482 |
|
| 1106 |
GRAVA TRITURADA 3/4" |
M3 |
0.4700 |
$87.600 |
$41.172 |
|
| 27 |
ACEITE MOTOR 4 TIEMPOS |
GLN |
0.0060 |
$117.290 |
$704 |
|
| SUBTOTAL |
$417.413 |
Mano de obra
| Código |
Descripción |
Unidad |
Cantidad |
Valor Unit |
Total |
Acción |
| 1381 |
M.O. 1 OFICIAL |
JORNAL |
0.1600 |
$108.356 |
$17.337 |
|
| 1390 |
M.O. 3 AYUDANTES |
JORNAL |
0.5400 |
$191.217 |
$103.257 |
|
| SUBTOTAL |
$120.594 |
Equipos
| Código |
Descripción |
Unidad |
Cantidad |
Valor Unit |
Total |
Acción |
| 1550 |
MEZCLADORA DE 9 PIES CUBICOS |
H |
0.6240 |
$5.151 |
$3.214 |
|
| 1166 |
HERRAMIENTA MENOR |
GLB |
0.0700 |
$94.094 |
$6.587 |
|
| SUBTOTAL |
$9.801 |